When installing lightning protection for telecommunications masts, three main issues must be taken into account. In our opinion, the best and most cost-effective way to dissipate the electrical charge is through the structure of the mast or lattice tower itself. AluPro products are equipped with a special eyelet in the lowest segment, which allows the entire structure to be connected to the building’s lightning protection system. For painted structures, be sure to remove…

Radio masts and towers require regular inspection and maintenance to prevent failures and life-threatening situations. Aluminum masts are corrosion-resistant but susceptible to frost cracking. The condition of guy wires and rope tension should be checked, and regular anti-corrosion inspections of steel structures are also necessary.

Updated: September 2026 · Legal status: August 2026 Short answer: Not to the environmental department. To the county administrator—yes, if the installation’s EIRP is 15 W or more. And this is a completely different requirement than the one discussed a few years ago. What has changed? Until June 2022, radio communication, radio navigation, and radar installations were listed…

Updated: September 2026 · Legal status: August 2026 The marking of a mast—including its paint scheme and lights—is determined by regulations governing aviation obstacles, not by its height alone, regardless of its location. A previous version of this post cited a 2003 regulation that has since been repealed; the thresholds we listed there are no longer in effect. When a mast is an obstacle…

Updated: September 2026 · Legal status: August 2026 It depends on the height of the structure and whether the installation interferes with the building’s structure. The old ruling we cited here (Provincial Administrative Court in Gdańsk, II SA/Gd 329/14) was based on a numbering system for the provisions that is no longer in effect following the 2020 amendment—which is why we are describing the current situation.…

Masts under 3 metres do not require a permit. Masts over 3 metres on buildings are subject to notification unless local regulations require a building permit.

The general rule is that guy wires should be arranged symmetrically—in three-cord masts, every 120° in the horizontal plane. As for the distance of the anchor point from the mast axis in the horizontal plane, it is assumed that it cannot be less than half the height of the mast. For example, for a 50-meter mast, the anchor point for the guy wires should be no closer than 25…

A telecommunications tower, like any truss, has node points that are its strongest areas. It is best to apply any forces in the vicinity of these points, as this minimizes the risk of localized damage to the structure. This is important in practice when installing additional guy wires, securing ropes during the rotational erection of a tower, and when selecting anchor points for antenna booms. A node is a point…

The separation ring serves two purposes. The first is to physically separate the transmitting antennas—such as sector antennas—from one another. Antennas emit back radiation, which can lead to interference and signal disruption. Since the strength of the electromagnetic field decreases with the square of the distance, even a small separation significantly reduces the mutual interference between antennas. It is worth checking the device specifications to determine the minimum…